Canary Cutover Runbook

How traffic moves from legacy hh-pegasus → monorepo hh-ionic (Cloudflare Pages / ionic.hungryhub.com). Incremental and reversible. Never flip 100% at once.

Owner: Irfan (Platform, execution) · Tompi (business go/no-go) · Saiqul (metrics).

Prerequisite: Gates 0–3 all ✅ (01-phases-and-gates.md).

Mechanism

Weighted routing at Cloudflare — Pages project / DNS weighting / Worker split. Coordinate the exact mechanism with hungryhub-terraform/hh-cloudflare before W8. Legacy stays deployed and instantly re-routable for the entire rollout.

Rollout stages

StageTrafficHoldRoutingWatch
Dogfoodteam + beta only3–5 daysheader/cookiemanual QA + error rate
Canary5% real users24–48hweightederror rate, conversion, p95 latency vs legacy
Ramp 125%48hweighted+ revenue/conversion delta
Ramp 250%48hweightedsame
Full100%1 week soakweightedsame, before decommission

Advance a stage only if all watch metrics are within agreed margin of legacy baseline.

Metrics to watch (per stage)

Captured by error monitoring + analytics wired in Phase 3:

  • JS error rate (Sentry or equiv) — monorepo vs legacy baseline
  • Booking conversion rate — funnel completion, monorepo cohort vs legacy cohort
  • p95 / p99 latency — page load + key API calls
  • Payment success rate
  • Core Web Vitals (LCP, CLS, INP) from real-user monitoring

Rollback triggers (any one → revert to previous % immediately)

  • JS error rate exceeds legacy baseline + agreed margin
  • Booking-conversion drop beyond statistical noise
  • p95 latency regression vs legacy
  • Payment failure spike
  • Any P1/P2 incident attributable to the monorepo app

Rollback procedure

  1. Set Cloudflare weight back to previous stage (or 0% → all traffic to legacy).
  2. Confirm legacy serving 100% and healthy.
  3. Open incident; capture error signatures + repro.
  4. Fix on a branch, add regression test (TDD), re-verify on staging.
  5. Resume rollout from the last good stage, not from where it failed.

Rehearse this procedure in staging during Phase 3 (task 3.4) before any real cutover.

Decommission (Gate 4 final)

Only after 100% + 1-week clean soak with no rollback trigger fired:

  1. Tompi confirms business sign-off.
  2. Irfan removes hh-pegasus infra (CF Pages project, DNS, build pipelines) via hungryhub-terraform.
  3. Archive legacy repo / mark read-only.